I'm a

Waikōwhai water pump station and watermains

Upgrades are required to cater for development in the Waikōwhai/Mt Roskill area.

Duration

Pump station (March 2023 – March 2024) and watermain (early 2025)

Location

Mt Roskill

Status

Construction

Get regular updates

The latest

We have finished laying the watermain and will return in March to complete the pipeline connections into the networks. This work will take approximately four months and involve less traffic management than our watermain construction.

Project overview

We are undertaking upgrades to the water network to cater for current and future development along with population growth. The current water network cannot cater for any further growth in the Waikōwhai/Mt Roskill area. This project will enable 4,000 dwellings that are proposed by Kainga Ora, plus 170 infill dwellings within the Waikōwhai/Mt Roskill area.

The proposal

  • Approximately 5,750 metres of watermains will be constructed, ranging in diameter from 300mm to 450mm. It is estimated the construction of the watermains will take approximately 18 months to complete
  • One new bulk supply point
  • A new booster pump station at 1374 Dominion Road (adjacent to the Akarana Golf Club) to replace the existing Hillsborough Pump Station

Completed sections of work

Please see the map below for the watermain sections that have been finished.

Waikōwhai Watermains Timeline 2/12/24 revised

Get in touch