Ōwairaka and Wesley water upgrades
New water upgrades are required to cater for development in Ōwairaka and Wesley areas.
Duration
2022 onwards
Location
Ōwairaka and Wesley
Status
Construction
The latest
Our contractor Fulton Hogan recently completed the early works package which included O’Donnell Avenue, Parkinson Avenue, Farrelly Avenue and Denize Road. Construction of a new bulk supply point chamber in the road near 2 La Veta Avenue and a pipeline connecting to an existing bulk supply chamber on Richardson Road was completed in early 2024.
Project overview
We are undertaking upgrades to the water network to cater for current and future development and population growth in the area. The project involves the construction of approximately 4,200 metres of new watermain with sections ranging from 200mm to 610mm in diameter, A new bulk supply point will also be constructed as part of the project. These works are supporting Kāinga Ora housing development in the area.
Current works
The map below shows each project area and the different stages of work.

Richardson Road- Oakley Creek pipe bridge works
Our crew started works in mid-February 2025 to construct a 610mm-diameter pipe adjacent to Richardson Road bridge which crosses over Oakley Creek. These works are progressing well and are estimated to take approximately a further four months to complete.
To support this work, a temporary platform will be built on the southern side of the bridge which will host a crane to assist with piling and installing the pipe. There will also be work on the northern side of the bridge where the retaining wall is located.
While the work is being carried out, and for the safety of the public, the Oakley Creek under-pass walkway and cycleway will be closed.
We will have a different way of getting to the other side of the bridge with lots of signs to guide you along the way.
Please refer to the below map for the works area.

La Veta Avenue connecting into the Mt Albert Ōwairaka Reservoir
Work to lay the watermain on the top section of La Veta Avenue and connect into the reservoir located on Mt Albert/Ōwairaka commenced in mid-January 2025. Works are progressing well and are on track to be completed by approximately May 2025. Please note we will need to return in May 2026 to complete our final connections in this area.
The proposed work includes the installation of a 610mm diameter pipe, which connects to the existing network located within Ōwairaka Domain. The installation will replace the redundant 310mm diameter pipeline and be installed using an open cut trench methodology.
While the removal of vegetation is required as part of the proposed works, once the works are completed replacement planting of native trees will take place. Replacement trees to be planted include Karamu, Houpara, Manuka, Mapou, Karo, Mahoe and Kowhai.
Please refer to the below map for the works area.

Denny Avenue
Our crew is making good progress on this section of works.
The estimated finish date for all works on Denny Avenue is May 2025.
How will this work affect you?
Work hours
- From 7am to 6pm Monday to Friday for the service investigations, and Monday to Saturday for the main construction works. Saturday work will only be utilised if required.
Traffic management
- Please allow extra time for travelling as there will be times when machinery will need to move to allow vehicles to pass by.
- Street parking within the work zone will be restricted. Please park within your property if possible.
- Pedestrian access will be maintained. There may be times where foot traffic is detoured to keep everyone safe. Please follow all posted signage.
Construction works
- Construction works will create noise, vibration, and dust. We will endeavour to keep disruption to a minimum and will be working in accordance with the levels under the Auckland Unitary Plan.