Herne Bay collector tunnel
A project aimed at delivering cleaner waterways and beaches by 2028.
Duration
2025 - 2028
Location
Herne Bay
Status
Design
Project overview
In parallel with the Central Interceptor extension to Point Erin, the Herne Bay collector tunnel will collect combined wastewater and stormwater overflows for safe treatment at Māngere Wastewater Treatment Plant. This new infrastructure will significantly reduce overflows into the environment and improve the quality of inland waterways and swimmable beaches by the end of 2028.
We will install a 2.1m-diameter tunnel for approximately 1.5km using a micro Tunnel Boring Machine (mTBM). Construction will occur sequentially over different road sections, with the pipeline passing beneath the road at depths ranging from 9-22 metres.
We will also:
- Install eight tunnel shafts, along with intercepting shafts connections to existing engineered overflow points (EOPs)
- Install small diameter pipelines along Marine Parade (600mm in diameter) and local connections to the existing engineering overflow points (between 200mm to 450mm in diameter). These will be constructed via open trenching.
- Establish two temporary Construction Support Areas (CSAs) one at Salisbury Reserve and the other in the area beside the Curran Street motorway on-ramp.
Salisbury Reserve temporary storage facility
Salisbury Reserve has been consented for use by the Herne Bay tunnel project as a temporary storage facility.
We have selected Italian company, Ghella, as the contractor for the project. The company is currently part of the Ghella Abergeldie Joint Venture, contractor for the Central Interceptor project. Ghella brings 150 years of international tunnelling experience to the new works. We aim to establish our first site in July 2025 and take around 36-40 months to complete.
Construction will occur sequentially over different road sections. We are working towards a start date of Q3 2025 for a 36-month construction programme. At present we are in design mode and will shortly begin the contractor selection process. We will provide updates as we approach each major project milestone.
The map below shows the location of the proposed works along with existing infrastructure and the Central Interceptor tunnel.
![Cleaner beaches Herne Bay project map September 2024](https://promising-sparkle-d7f0c0cfc9.media.strapiapp.com/cleaner_beaches_herne_bay_map_sept_24_8547a9554a.jpg)
Point Erin Park: South-west corner works
We are making good progress planning for the Point Erin Park south-west corner works (control chamber and plant room), which will integrate with the main Herne Bay tunnel (HBT) project. The image below shows amended design of the control chamber as well as the location of the first HBC shaft which has been moved into the park. We have our refined thinking around the connections to the EOP (engineered overflow point).
We will commence required early works, service relocations in the main, from mid-2025, followed by shaft excavation over the summer.
![Schematic Jan 2025](https://promising-sparkle-d7f0c0cfc9.media.strapiapp.com/schematic_jan_2025_8fd5e15c5b.png)
St Marys Bay and Herne Bay separation projects
These projects were earlier works that focused on separating the old, combined stormwater and wastewater pipes.
Herne Bay collector tunnel consent documents
Herne Bay collector tunnel consent documents
Consent Lodgement - July 20231 Herne Bay Trunk sewer AEE pdf
Appendix A Permitted Activities pdf
Appendix B Proposed Conditions pdf
Appendix C Records of Title pdf
Appendix D1 Geotechnical Assessment pdf
Appendix F Integrated Traffic Assessment pdf
Appendix G Arboricultural Assessment pdf
Appendix H Archaeological Assessment pdf
Appendix I General Arrangement Drawings pdf
Appendix J Construction Methodology pdf
Appendix K1 Noise and Vibration Assessment pdf
1 Herne Bay Trunk sewer AEE pdf
Appendix A Permitted Activities pdf
Appendix B Proposed Conditions pdf
Appendix C Records of Title pdf
Appendix D1 Geotechnical Assessment pdf
Appendix F Integrated Traffic Assessment pdf
Appendix G Arboricultural Assessment pdf
Appendix H Archaeological Assessment pdf
Appendix I General Arrangement Drawings pdf
Appendix J Construction Methodology pdf
Appendix K1 Noise and Vibration Assessment pdf
Updated Consent Lodgement - August 2023Methodology Cover Letter - 8 August 2023
s92 Updated Herne Bay Trunk Sewer Assessment of Environmental Effects - 7 August 2023 v3
s92 Proposed Conditions - 7 August 2023
Construction Methodology - 8 August 2023
Draft of Construction Noise & Vibration Management Plan - 3 August 2023 v1
Construction Noise & Vibration Assessment - 3 August 2023 v1
Methodology Cover Letter - 8 August 2023
s92 Updated Herne Bay Trunk Sewer Assessment of Environmental Effects - 7 August 2023 v3
s92 Proposed Conditions - 7 August 2023
Construction Methodology - 8 August 2023
Draft of Construction Noise & Vibration Management Plan - 3 August 2023 v1
Construction Noise & Vibration Assessment - 3 August 2023 v1
s92 Response & Updated Documentation - October 2023Resource Consent Application - s92 Request - 1 September 2023
s92 Response Letter - 5 October 2023
Attachment A: Groundwater & Settlement Assessment Report - September 2023 v4
Attachment B1: Erosion & Sediment Control- Site Plan - 22 September 2023 v2
Attachment B2: Draft Erosion & Sediment Control Plan Report - 22 September 2023 v2
Attachment C: Construction Noise & Vibration Technical Assessment - August 2023 v1
Attachment D: Construction Noise & Vibration Management Plan - September 2023 v1.1
Attachment E1: CSA-1 Concept Layout Plan
Attachment E2: CSA-2 Concept Layout Plan
Attachment G: Arboricultural Assessment of Effects - 9 June 2023
Attachment H: Proposed Salisbury Reserve Reinstatement Concept Sketch - 7 September 2023
Attachment I: Approved Reserve Reinstatement Plan 94a - 94b Shelly Beach Road - 23 March 2021
Attachment J: Street Tree Replanting Memo & Plans - 7 September 2023
Herne Bay Trunk Sewer: Amendments To Application - 13 October 2023
Resource Consent Application - s92 Request - 1 September 2023
s92 Response Letter - 5 October 2023
Attachment A: Groundwater & Settlement Assessment Report - September 2023 v4
Attachment B1: Erosion & Sediment Control- Site Plan - 22 September 2023 v2
Attachment B2: Draft Erosion & Sediment Control Plan Report - 22 September 2023 v2
Attachment C: Construction Noise & Vibration Technical Assessment - August 2023 v1
Attachment D: Construction Noise & Vibration Management Plan - September 2023 v1.1
Attachment E1: CSA-1 Concept Layout Plan
Attachment E2: CSA-2 Concept Layout Plan
Attachment G: Arboricultural Assessment of Effects - 9 June 2023
Attachment H: Proposed Salisbury Reserve Reinstatement Concept Sketch - 7 September 2023
Attachment I: Approved Reserve Reinstatement Plan 94a - 94b Shelly Beach Road - 23 March 2021
Attachment J: Street Tree Replanting Memo & Plans - 7 September 2023
Herne Bay Trunk Sewer: Amendments To Application - 13 October 2023
s92 Further Information Responses - November - December 2023
Hearing EvidenceHearing Evidence of Andrew Clarke (Structural Engineering) - 2 February 2024
Hearing Evidence of Andrew Deutschle (Corporate) - 2 February 2024
Hearing Evidence of Colin Shields (Transport) - 2 February 2024
Hearing Evidence of Jeremy Elley-Brown and William Hung (Consultation) - 2 February 2024
Hearing Evidence of Julia Wick (Landscape and Visual) - 2 February 2024
Hearing Evidence of Maree Drury (Planning) - 2 February 2024
Hearing Evidence of Mark Thomas (Geotechnical) - 2 February 2024
Hearing Evidence of Rory Bishop (Construction Methodology) - 2 February 2024
Hearing Evidence of Sean McBride (Arboricultural) - 2 February 2024
Hearing Evidence of Sharon Yung (Noise and Vibration) - 2 February 2024
Hearing Evidence of Stephen Webster (Corporate) - 2 February 2024
Hearing Evidence of Andrew Clarke (Structural Engineering) - 2 February 2024
Hearing Evidence of Andrew Deutschle (Corporate) - 2 February 2024
Hearing Evidence of Colin Shields (Transport) - 2 February 2024
Hearing Evidence of Jeremy Elley-Brown and William Hung (Consultation) - 2 February 2024
Hearing Evidence of Julia Wick (Landscape and Visual) - 2 February 2024
Hearing Evidence of Maree Drury (Planning) - 2 February 2024
Hearing Evidence of Mark Thomas (Geotechnical) - 2 February 2024
Hearing Evidence of Rory Bishop (Construction Methodology) - 2 February 2024
Hearing Evidence of Sean McBride (Arboricultural) - 2 February 2024
Hearing Evidence of Sharon Yung (Noise and Vibration) - 2 February 2024
Hearing Evidence of Stephen Webster (Corporate) - 2 February 2024