I'm a

Central Interceptor

The largest wastewater project in New Zealand, our super-sized tunnel will run for 16.2kms under Auckland city and the Manukau Harbour. Find out what it’s all about and how we’re tracking.

Duration

2019-2026

Location

Herne Bay to Māngere

Status

Construction

Hiwa-i-te-Rangi completes her epic journey

On 28 March, Auckland Mayor Wayne Brown gave the order for our TBM to start up for the last time to finish the final few centimetres of her 16.2km journey since being launched from Māngere Wastewater Treatment Plant in July 2021.

At a special celebration event, 250 guests gathered around the 30-metre- deep shaft to watch the action as it was livestreamed onto a large screen. Slowly, the 5.2m diameter cutterhead emerged through billowing dust, chewing its way through the final centimetres of the concrete shaft wall—and into daylight.

Tunnellers have worked 24 hours per day, six days a week to build the tunnel. Hiwa-i-te-Rangi laid eight to 10 rings and travelled around 22 metres per day. The concrete rings are coated with a plastic liner to protect against the corrosive effects of wastewater, to ensure the tunnel lasts 100 years.

In coming weeks, she will be removed from the shaft in sections. Thermal welding on tunnel segment joins will ensure the tunnel is air-tight and services such as locomotive tracks will be removed. Elsewhere, the tunnel will continue to be connected to the existing wastewater network.

Southern section of our tunnel is ‘switched on’

Our CI project has passed an historic milestone with the southern half of the tunnel going live and operational. This section, Blockhouse Bay east to May Road (Link Sewer C), then south to Māngere Wastewater Treatment Plant, is 10.8km long. We are now one step closer to the goal of cleaner inland waterways and open spaces for central Auckland.

We held a formal celebration event on 14 February in our new pump station at the treatment plant, attended by Minister for Local Government Simon Watts, Auckland Mayor Wayne Brown, local elected members and project teams. Around 200 guests lined the pump station shaft as Mayor Brown gave an order to start up the new giant pumps. These send wastewater flows from the tunnel to the treatment plant at a rate of 1,200 litres per second.

It was an historic moment as we recognised the accomplishments of the 600 members of the Watercare and Ghella Abergeldie JV project teams, which began construction in 2019.

Turning on southern section

See how far we've tunneled

See what our three Tunnel Boring Machines have achieved

What are we building under there?

The Central Interceptor tunnel lies between 15 and 110 metres below the city surface and will run all the way from Pt Erin in Herne Bay to Māngere Wastewater Treatment Plant. With a diameter of 4.5m, the tunnel will be high enough to fit a standing giraffe inside.

Along with two smaller-link sewer tunnels also under construction, the main CI tunnel will collect wastewater from the existing network and take it to Māngere, with a controlled flow rate. The tunnel slopes at a gradient of 1:1000 so wastewater can flow downhill to Māngere.

The budget for this epic seven-year project is $1.668 billion.

Did you know?

The CI tunnel has capacity to store more than 250,000 cubic metres of wastewater - that’s 99 Olympic swimming pools. Read more in our project brochure.

Photo of the Central Interceptor mobile Discovery Centre.

Check out our travelling Discovery Centre

Grab the whānau and join us for an awesome experience including virtual reality, outdoor games and a movie ride to learn all about the CI tunnel. Here's where our Discovery Centre will be:

March

  • Friday 28 March, 5.30pm-9pm: Junk & Disorderly carpark, 164 Balmoral Road, Mt Eden
  • Saturday 29 March, 10am-3pm: Ambury Farm, Māngere Bridge

April

  • Saturday 5 April, 10am-1pm: Little Day Out, Mt Eden Village Centre
  • Saturday 5 April, 10am-4pm: MOTAT Stem Fair
  • Sunday 6 April, 10am-4pm: Māngere Bridge Family Festival, Coronation Road
  • Saturday 12 to Thursday 17 April, all day: Auckland Museum (at ‘Imaginary)
  • Sunday 13 to Tuesday 15 April, all day: Epsom Library, 195 Manukau Road by the main entrance
  • Friday 18 to Monday 21 April, all day: Easter Show, outdoors at Auckland Showgrounds, Greenlane Road, Epsom

Construction updates

We have 17 construction sites along the tunnel route, with some operating for three to five years, with smaller sites open for around 24-36 months.

At the bottom of the page, you can see what’s going on at each site.


The technology behind New Zealand’s largest wastewater project

To dig the main CI tunnel and lay the concrete segments behind it, we’re using state-of-the-art tunnel boring machines or TBMs. These gigantic machines enable us to excavate (or ‘bore’) through a wide range of ground conditions.

Infrastructure constructed by these powerful TBMs is strong and reliable and is set to last at least 100 years.

Photo of the tunnel boring machine Hiwa-i-te-Rangi being unveiled.

Meet Hiwa-i-te-Rangi: a truly ground-breaking machine

Hiwa-i-te-Rangi is the giant TBM working tirelessly to grind a 16.2 km journey, using her massive cutter head.

TBMs are traditionally given female names in honour of the patron saint of miners and tunnellers, Saint Barbara.

To find a name for our main TBM, we asked for ideas from children in schools along the tunnel route. They chose Hiwa-i-te-Rangi, a female Matariki star, which they believed represented our aspiration to improve the natural environment.

Hiwa-i-te-Rangi is in great company, working alongside our smaller TBMs, Dominica and Victoria (and our training TBM, Kate).

Did you know?

We truck up to 5,000 cubic metres of rock and soil (or ‘spoil’) each week – that's enough to fill up more than 150 six-metre-long sea containers. Most of the spoil is taken to Puketutu Island in Māngere to help restore the original volcanic cone. One day, this island will be opened to the public as a regional park.

Engaging with locals

We want to update you on the construction process and hear your feedback. If you live or work near one of our sites, you’ll get a bulletin, newsletter, notice or letter, or an invitation to a public event, depending on the information we have to share.

You can also come along to our interactive travelling Discovery Centre to know more about what’s going on and have some fun at the same time (details above). Email us your feedback.


Supporting our wider community

Although it’s being built to last 100 years, the ambition for the project extends well beyond construction. We also want to help improve the well-being of communities along the tunnel route.

To support this, a cultural outcomes group is providing advice as the project progresses. This group comprises people from Mana Whenua, our Watercare team and contractors. Check out some of our activities.


Protecting our environment

As well as delivering significant environmental benefits such as cleaning up our waterways, we’re committed to leaving our construction sites and their surrounds in a better condition than when we arrived.

Learn more about our plans, initiatives and practical actions in the areas of sustainability and the environment.

Updates from our sites across Auckland

Dundale Avenue - Construction began: July 2020
Frederick Street (PS23) - Construction began: July 2021
Haverstock Road - Construction began: April 2022
Haycock Avenue - Construction began: May 2020
Keith Hay Park - Construction began: January 2020
Lyon Avenue - Construction date: May 2022
Māngere Pump Station - Construction began: August 2019
May Road - Construction began: August 2019
Miranda Reserve incl PS25 - Construction began: 29 September 2020 (Blockhouse Bay Road site) and November 2021 (PS25 site)
Mt Albert War Memorial Reserve - Construction began: May 2022
Norgrove Avenue - Construction began: November 2022
Rawalpindi Reserve - Construction began: October 2022
Tawariki Street, Grey Lynn - Construction began: 2023
Walmsley Park - Construction began: December 2020
Western Springs - Construction began: 2022
Pt Erin - Construction began: June 2024